Business Opportunities
NRG Stadium Ramp Corrosion Repair
Work includes corrosion repairs and recoating and other scope items on the four exterior ramps of NRG Stadium
Due Date: 2/5/2026 3:00:00 PM
NRG Park Boiler Replacement
All labor, equipment, materials, and incidentals necessary for the replacement of boilers and ancillary systems and equipment serving NRG Park. Mandatory Site Visit at NRG Central Plant 1/29/26, 11:00am
Due Date: 2/9/2026 1:00:00 PM
NRG Park Marquee Replacement
Contractor to furnish all labor, equipment, materials, and incidentals necessary to complete the Gate 8 Upgrade which will include the renovation and modernization of the existing entry sequence to improve access throughput, ticketing efficiency, and overall guest experience.
SCHEDULE
CSP Documents Issuance - 02-06-2026
Site Visit - 02-12-2026 at 12:30pm (NRG Park, Houston)
Questions Due - 02-13-2026 at 3:00 pm
Answers - 02-16-2026
CSP Due Date - 02-23-2026 at 1:00 p.m.
Bid Award- 02-27-2026
Construction Start – 03-30-2026
All Work Complete – 05-15-2026
Due Date: 2/23/2026 1:00:00 PM
NRG Park Gate 8 Upgrades and Repairs
Contractor to furnish all labor, equipment, materials, and incidentals necessary to complete the Gate 8 Upgrade which will include the renovation and modernization of the existing entry sequence to improve access throughput, ticketing efficiency, and overall guest experience.
SCHEDULE
CSP Documents Issuance - 02-06-2026
Site Visit - 02-12-2026 at 12:30pm (NRG Park, Houston)
Questions Due - 02-13-2026 at 3:00 pm
Answers - 02-16-2026
CSP Due Date - 02-23-2026 at 1:00 p.m.
Bid Award- 02-27-2026
Construction Start – 03-30-2026
All Work Complete – 05-15-2026
Due Date: 2/23/2026 1:00:00 PM